SECURITY FACILITIES

Technological solutions

Management methodology and ADLC standards

INVESTIGATION

2010

Formal and funtional study of the infrastucture of the prision of Trujillo - El Milagro

2012

Urban impacts in the immediate contex, due to the presence of a prison in Trujillo - El milagro

2013

Optimization of the prison infrastructure through the application of virtual design and construction

2017

Optimization of the prison infrastructure through the application of virtual design and construction

2018

BIM management for the virtual construction of prison infrastructure projects

2018

FINALIST IN GOOD MANAGEMENT PRACTICE: "BIM MANAGEMENT IN THE VIRTUAL CONSTRUCTION OF INFRAESTRUCTURE PROJECTS"
TO SERVE

2017

GOOD PRACTICE IN PUBLIC MANAGEMENT: "OPTIMIZATION OF PRISON INFRASTRUCTURE THROUHG THE APPLICATION OF VIRTUAL DESIGN AND CONSTRUCTION"
CITIZENS A DAY

2014

FIRST PLACE YOUTH SCIENTIFIC DAY
NATIONAL ASSEMBLY OF RECTORS

2013

FIRST PLACE CONTEST STRUCTURE YOUR IDEAS
GRAÑA Y MONTERO ENGINEERING PORTAL

2013

FIRST PLACE YOUTH SCIENTIFIC DAY
ANTENOR ORREGO PRIVATE UNIVERSITY

TECHNICAL FILES

DEPARTMENT UNITS EP CHINCHA
Roofed Area 18,418.25 m2
Reference Amount: S/. 55.2 Million
Shelter capacity 1032 ua (before 528 ua)
PAVILION EP JAUJA
rOOFED AREA 1,640.00 m2
Reference Value: S/. 7.7 Million
Shelter capacity 288 ua (before 240 ua)
PAVILIONS EP CAJAMARCA
Roofed Area 3,693.53 m2
Reference Value: S/. 17.5 Million
Shelter capacity 432 ua (before 232 ua)

TECHNICAL CONSIDERATIONS

WORKS CONTROL

EP Puno Pavilion
Roofed Area 1,560.00 m2
Reference Value: S/. 4.9 Million
EP Chincha Internment Unit
Roofed Area 18,418.25 m2
Reference Value: S/. 55.2 Million
EP Cajamarca Pavilion
Roofed Area 3,693.53 m2
Reference Value: S/. 17.5 Million
EP Chimbote Pavilion
Roofed Area 1,940.00 m2
Reference Value: S/. 8.9 Million
EP Trujillo Pavilion
Roofed Area 1,397.93 m2
Reference Value: S/. 5.9 Million
EP Jauja Pavilion
Roffed Area 1,640.00 m2
Reference Value: S/. 7.7 Million

TRIPLE BUNK

TRIPLE BUNK

Hostel capacity 09 ua
Roofed area 19.2 m2
Ratio per inmate 2.1

DOUBLE BUNK

Hostel capacity 08 ua
Roofed area 24.6 m2
Ratio per inmate 3.1

GREATER HOSTING CAPACITY

TYPE PAVILION - CELL 08

Shelter capacity 192 ua
Number of cells 24 (capacity 08 ua)
Roofed area 775.8 m²
Ratio per inmate 4.0
Living room area 94 m² x2=1m²/internal
Patio area 295 m² x 2=3m²/internal
Dining area 94 m² x 2= 1m²/internal
Number of showers 12 = 1/16 internal

PAVILION PLUS - CELL 12

Shelter capacity 240 ua
Number of cells 20 (capacity 12 ua)
Covered area 786.5 m²
Ratio per inmate 3.3
Living room area 118 m²X2 = 1 m² / internal
Patio area 387 m²X2 = 3.2 m² / internal
Dining area 118m² x 2= 1m² / internal
Number of showers 8 = 1/30 internal

PAVILION PLUS X - CELL 12

Shelter capacity 288 ua
Number of cells 24 (capacity 12 ua)
Roofed area 916.7 m²
Ratio per inmate 3.2
Living room area 118 m²x2 = 8m² / internal
Patio area 465 m²x2 = 3.2m² / internal
Dining area 118 m²x2= 8m² / internal
Number of showers 8 = 1/36 / internal

MODERNIZATION OF THE PENITENTIARY SYSTEM

SEEK CONTINUOUS IMPROVEMENT

EFFICIENT DESIGN WITH CUTTING-EDFE TECHNOLOGY

PRODUCTIVE PENITENTIARY ESTABLISHMENT SHUMBA JAÈN

NEW PENITENTIARY MODEL

04 Independent detention modules

03 Pavilions of 24 cells by pavilions of 24 cells for each interment module

Maximum capacity for 3456 inmates

Roofed area 701,000.00 m²

Estimated investment amount 350 million

02 production hangars for private companies (DL 1343)

TOTAL CONTROL

Sustainable Prison Establishment

enviromental friendly

Crossed ventilation

Venturi effect

Incidence of the wind in the project

SIGEINPE

INTEGRAL PENITENTIARY MANAGEMENT SYSTEM

Control center

Data center

Surveillance room

Control cabins

CONTROL BUILDING

VISUAL CONTROL

VIDEO SURVEILLANCE

ACCESS CONTROL

DEMOSTRATION PAVILION